Our project

The most significant projected work is the construction of a building intended to accommodate the orphans.  For the time being, the few children to be lodged in the orphanage are hosted by one of the people in charge of the orphanage. Thus, this project is urgent.  Please note that the CEMI/DES has already has a plot  where a two level building can be built.
 

 

 

 The cost of construction amounts to roughly 62 800 €. A more technical study and detailed description of the project is underway at a local technical office which proposes the outlines below.  


                                     

                                 Cut of the plan of the orphanage                  Plan of a frontage


                                                        

                                                                Plan of another frontage

In addition to the building, it will be necessary to invest in the material and the provisions so that the orphanage is operational. Hereafter is an approximate evaluation of the needs. 

 

Examples of capital cost (calculation based on 20 children)   

 

1- Cost of the materials for the dormitories and the refectory (PU and in euro)  

 

Descriptive of the investment  

Unit

Qty   

PU

Amount

1

2

3

4

5

6

7

8

9

Batch of 2 bunk beds   

Mattress per place   

Pillows

Office chairs

Tables

Benches   

Tablecloths

Mattress covers  

Mosquito nets 

U

U

U

U

U

U

M

U

U

10

20

20

2

2

4

14

40

20

34,62

19,23

1,92

10

42,31

9,63

2,69

1,23

2,69

346,16

384,62

38,4

20

84,62

36,92

37,69

49,23

53,85

TOTAL :          1051,49 €

 

2- the cost of the materials of kitchen (PU and in euro)  

 

Descriptive of the investment  

Unit

Qty   

PU

Assembling    

1

2

3

4

5

6

7

8

9

10

11

Pot (large model)

Pot (average model)

Batch of 12 plates   

Batch of 12 spoons   

Plate (large model)

Spoon (large model)

Batch of 12 forks   

5 liter bucket

200 liter freezer

Gas burners (4fires)

Bottle of gas   

U

U

U

U

U

U

U

U

U

U

U

2

3

2

2

4

4

2

4

1

1

4

26,92

19,23

9,62

5,00

6,92

0,92

5,00

2,69

384,23

180,50

26,92

53,95

57,69

19,24

10,00

27,68

3,68

10,00

10,77

384,23

180,50

107,68

TOTAL : 865,42 €

3 Cost of the provisions per month (PU and in euro)  )

 

Descriptif of the provisions   

Unit

Qty

PU

Assembling    

1

2

Charcoal   

Provisions for 3 meals per day   

Bag   

U

6

26

2,31

46,15

13,85

1200,00

TOTAL : 1213,85 €

 